Trond Lunde
Trond has extensive experience with the financial follow-up of projects in the construction industry at the project level and overall level. Trond has worked with projects from calculation to final settlement and has good knowledge of challenges, current laws and regulations, NS, and criteria for success in the various phases of projects. Both turnkey contracts, main contracts, and subcontracts.
Good system and accounting understanding Visma business / document center, Agresso, Map, Byggoffice, Eye-share, Tripletex, 4PS.
Trond’s career started at Skanska as a project and regional controller in 2005. In 2016, he started working at Risa as a finance manager for the energy and industry department. Works as CFO in Energy Consult today, in addition to being engaged as a consultant on the finance side for an international construction company.
Profile
Education
Bergen University College
2001-2004
Bachelor in economy and administration
Metier / NTNU Project management and project management, best practice
Key qualifications
Financial follow-up of project
Calculation / Purchasing
Contract follow-up / change management
Final settlement
Relevant experience
Kvitfjell wind farm
Finance manager on project for the turnkey contractor, personnel, and process responsibility for the finance function in the project. Turnkey contract 2017-2019
Åseral Nord - rockfill dam
Finance manager on project for the basic contractor, quantity-regulated main contract.2018-2019.
Tonstad wind turbine
Finance manager on project for the turnkey contractor, personnel, and process responsibility for the finance function in the project. Turnkey contract 2018-2019
Trond LundeFinance Manager / Partner +47 924 30 705 trond.lunde@energy-consult.no
Trond LundeFinance Manager / Partner +47 924 30 705 trond.lunde@energy-consult.no
Experiences
Mutkalampi Wind Farm 302MW
Wind turbines - Form of contract:
EPC contract - Year of construction
2019
Microsoft Data Center AMS13 og AMS14
Datacenter - Form of contract:
Turnkey contract. - Year of construction
2019
Mastokangas Wind Farm 50MW
Wind farm - Form of contract:
EPC contract - Year of construction
2019
Experiences
Mutkalampi Wind Farm 302MW
Wind turbines - Form of contract:
EPC contract - Year of construction
2019
Microsoft Data Center AMS13 og AMS14
Datacenter - Form of contract:
Turnkey contract. - Year of construction
2019
Mastokangas Wind Farm 50MW
Wind farm - Form of contract:
EPC contract - Year of construction
2019